Update a job run time
Qualifiers
You want to modify the time or times a job runs
Process
Navigate to the Scheduler / Job tab
Check if the job is a child. The parent job controls the run times. If the job is a child, either
Update the run times in the parent job.
Parent Job ID click to hyperlink to the parent job. Go to step 4.
Decide to remove the job from the Parent-Child chain to run the job separately
Click on Edit button
Parent Job ID - remove number from this field. Go to step 5.
Click on Edit button
Make the changes the Run Times section
Minutes: - click on the minute, minutes or range of minutes you want the job to run on
E.g. choosing 0, 15, 30, 45 would run the job every 15 minutes for the selected run hours.
'All' is not a recommended setting.
Hours: - click on the hour, hours or range of hours you want the job to run on.
E.g. choosing 6am-9pm would run the job every 15 minutes from 6:00am to 9:45pm
Days: - click on the days you want the job to run on. Choose 'All' to run the job on any day.
Months: - click on the months you want the job to run on. Choose 'All' to run the job in any month.
Weekdays: - click on the specify days you want the job to run on.
Monday - Friday is a popular choice for business process jobs and emails.
Click on Save button